Risk Schedule Assessment Download

Schedule Risk Analysis Framework
Risk & Schedule Assessment Guide
Know What to Expect
- Documentation Required
- Key Participants
- Software Utilized
- Timeline
- Workshop Process
- Deliverable Reporting
D800 – Jeopardy

Tower Crew wait time while operations prepares equipment
A. Direct Field Labor – Columns & Towers
Incorrect
B. Direct Field Labor – Cooling Tower
Incorrect
C. Direct Field Labor – Operations Shutdown / Startup
Incorrect
D. Admin & Overhead – Time Delayed Work
Correct
C800 – Jeopardy

Rescue Team for Tank Entry
A. Direct Field Labor – Tanks / Drums / Vessels / Filters
Incorrect
B. Admin & Overhead – Health / Safety / Environmental
Correct
C. Admin & Overhead – General & Administrative
Incorrect
D. Direct Field Labor - General
Incorrect
B800 – Jeopardy

Transportation Fees for Control Valve
A. Material – Contractor Purchased Material
Incorrect
B. Direct Field Labor – Control Valve
Incorrect
C. Material – Hot Shots
Correct
D. Material – Site Purchased Material
Incorrect