Utilizing Different Methods to Remove Logic in Primavera P6
Utilizing Different Methods to Remove Logic in Primavera P6 There are multiple ways to remove logic from a P6 schedule. Below are four examples of how this can be accomplished. Method #1 – Using the...
Managing Lag Utilizing a Time Delay Activity in P6
Understanding Lag Lag is a duration that is applied to a dependency to make the successor start or finish earlier or later. Lag can be positive or negative and it is based on the calendar of the...
Filter Activities Within a Specific Timeframe
To filter for activities within a specific timeframe, create the following filter: For this example, the timeframe is August 28, 2005, through September 3, 2005. When creating your filter,...
Copy a WBS Structure into a New Project
Goal: How to copy the WBS structure from an existing project into a new project. There are two ways to copy the WBS information from one project to another. Project that has the WBS structure...
Copying Activities to Another Project While Maintaining WBS Structure
Goal: How to copy activities to another project while maintaining their WBS structure in the new schedule. Open both the source and destination projects. Select, Project, WBS Highlight the WBS...
Hot Keys and Icon Definitions for Project Management
ALT – F: File MenuALT – N: New… or Crtl+NALT – O: Open… or Crtl+OALT – S: Close All or Crtl+WALT – L: Login as a Different User…ALT – U: Page Setup…ALT – V: Print PreviewALT – P: Print… or Ctrl+PALT...